Installation Precautions for Elastic Vibrating Rappers
To deal with the problems that customer units most often run into during installation, the engineers of Hunan Darui Heavy Machinery Co., Ltd. give the following recommendations:
1. When installing the equipment, fill the gear reducer housing with lubricating oil for the gear reducer.
2. Pump grease into the oil hole at the end of the main shaft; grease should be seen squeezed out on both sides of the rotating shaft.
3. The distance from the hammer head of the pendulum assembly of the high-efficiency elastic vibrating rapper to the load-bearing beam on the boiler is the length of the force-transfer part; verify it on site before welding.
4. Weld the force-transfer rod to the related part on the boiler, using 506 welding rods, and make sure the welding does not produce any additional bending stress when the rapping force is transmitted; reinforce the welding points with stiffening plates.
5. Fix the adjusting bracket of the equipment; during installation make sure that in the working state (hot state) the hammer head of the pendulum assembly contacts the spring anvil contact surface properly.
6. Check whether the power supply circuit has an overcurrent protector designed for every rapper. When wiring, pay close attention to the chain rotation direction arrow marked on the equipment: open the rear cover of the housing at this point and observe whether the pendulum assembly and the chain move in the correct direction. Correct wiring makes the hammer head rise slowly while the chain moves in the marked direction. Wrong wiring reverses the chain rotation direction and will damage the equipment!