Operation, Maintenance and Installation of Belt Conveyors

Category: Technical  |  Published: 2024-03-26
I. Starting and stopping Conveyors should generally be started under no-load conditions. When several belt conveyors are installed in sequence, an interlocked starting device should be used so that they can be started and stopped in a fixed order from the central control room. Besides this, to guard against sudden accidents, each conveyor should also be provided with a local start/stop button so that any one of them can be stopped separately. To keep the conveyor belt from being torn lengthwise for some reason, conveyors longer than 30 m should have a stop button installed along the whole length of the conveyor at a fixed interval (for example every 25-30 m).
      II. Maintenance of the belt conveyor To keep the belt conveyor running reliably, the most important thing is to discover and remove possible faults in time. Therefore the operator must observe the working condition of the conveyor at all times and deal with any abnormality promptly. Maintenance workers should periodically patrol and inspect any condition or part that needs attention; this is very important. For instance, one idler roller may look insignificant, but a high-speed conveyor belt carrying abrasive material can soon wear through its shell and produce a cutting edge, and that edge can seriously damage a costly conveyor belt. Trained or experienced workers can discover an impending accident in time and prevent it before it happens. The conveyor belt accounts for a considerable share of the total cost of the conveyor. To reduce the cost of replacing and repairing belts, attention must be paid to training operators and maintenance staff in belt running and repair knowledge.
      III. Installation of the belt conveyor Installation of a belt conveyor is generally carried out in the following stages.
      1) Installing the frame of the belt conveyor Frame installation starts with the head frame, then each intermediate section is installed in order, and the tail frame is fitted last. Before installing the frame, a centre line must be stretched along the whole length of the conveyor, because keeping the conveyor centre line straight is an important condition for normal belt travel, so when each frame section is installed it must be aligned with the centre line and the frame must also be levelled; the permitted deviation of the frame from the centre line is +/-0.1 mm per metre of frame length, but the deviation of the frame centre over the whole length of the conveyor must not exceed 35 mm. Once all single sections are fitted and aligned, they can be joined together.
      2) Installing the drive unit When installing the drive unit, make sure the transmission shaft of the belt conveyor is perpendicular to the conveyor centre line, the middle of the width of the drive drum coincides with the conveyor centre line, and the axis of the gear reducer is parallel to the transmission axis. At the same time all shafts and drums must be levelled. The permitted horizontal error of the shaft, depending on how wide or narrow the conveyor is, lies in the range 0.5-1.5 mm. While the drive unit is installed, the tail wheel and other tensioning devices can be installed too; the drum axis of the tensioning device must be perpendicular to the conveyor centre line.
      3) Installing the idler rollers. After the frame, the drive unit and the tensioning device are installed, the idler roller racks for the upper and lower idlers can be installed so that the belt forms an arc that changes direction gradually; the spacing of the idler racks in the bending section is 1/2 to 1/3 of the normal idler rack spacing. After the idler rollers are installed, they must rotate freely and lightly.
      4) Final alignment of the belt conveyor. To keep the belt always running on the centre line of the idler rollers and drums, the following requirements must be met when installing the idler rollers, the frame and the drums:
      (1) All idler rollers must be lined up, parallel to each other and kept horizontally level.
      (2) All drums must be lined up and parallel to each other.
      (3) The supporting structure racks must form a straight line and keep horizontal levelling. For this reason, after the drive drum and the idler racks are installed, the centre line and the level of the conveyor must be finally corrected.
      (4) Then the frame is fixed to the foundation or the floor slab. Once the belt conveyor is fixed, the feeding and discharging devices can be fitted.
      (5) Hanging the conveyor belt. When hanging the belt, first lay the belt strip on the idler rollers of the empty section, wrap it around the drive drum, and then lay it on the idler rollers of the loaded section. A hand winch of 0.5-1.5 t can be used to hang the belt strip. When the belt strip is tensioned and joined, the drum of the tensioning device must be moved to the limit position: for trolley and screw-type tensioning devices pull towards the drive unit, and for vertical tensioning devices move the drum to the topmost position. Before the belt is tensioned, the gear reducer and the motor must already be installed, and an inclined conveyor must have its braking device fitted. After installation the belt conveyor must be tested running empty.
      During the empty-run test, watch whether the belt runs off centre while travelling, the running temperature of the drive part, the freedom of the idler rollers in motion, and how tightly the cleaning device and the guide plates contact the belt surface; make the necessary adjustments at the same time, and only after every part is normal may the load-bearing running test be carried out. If a screw-type tensioning device is used, its tightness must be adjusted once more during the loaded running test.